π§ Construction on the Alliant Energy battery expansion project was scheduled to begin this month, but Union County tabled the decision until Wednesday, May 20.
βοΈ The Creston Solar and Battery Energy Storage System has been in motion since 2022 after receiving its initial construction permit for a 40 MW solar field and 25 MW battery system.
π A BESS system stores energy to ensure a steady flow during fluctuations when the solar field cannot generate power.
π The foundation for the 25 MW BESS already broke ground in 2024, with plans for mobilization this month pending equipment delivery.
ποΈ The original construction permit waives setback restrictions, allowing the project to be located east of Creston on an existing solar field site.
β³ Sean Keenan from Alliant stated that a six-month timeline would make the BESS operational by December if construction starts on time.
π The board is reviewing a major amendment that expands the BESS operating capacity from 25 MWs to 40 MWs using additional equipment within the same footprint.
β οΈ Supervisor Rick Friday cited the county's moratorium on solar energy systems as a reason the amendment could not be approved without reconsidering the location.
πΈ Alliant presented a parental guarantee covering approximately $1.757 million in decommissioning costs, including salvage and disposal fees.
π₯ Safety concerns remain regarding lithium battery fires, which require managing extinguishing efforts while mitigating health risks from harmful emissions.
π‘οΈ EMA Coordinator Paul Ver Meer approved the emergency plans submitted by Alliant for Union County Fire Department collaboration.
βοΈ Sarah Franklin, an attorney for Alliant, argued the amendment does not break restrictions because it stays within the same footprint and is not a change in character.
π° The county's moratorium was originally placed due to supervision concerns over taxation, specifically the need for definitive numbers rather than estimates.
π± Supervisor Dennis Hopkins expressed concern that expanding storage without additional generation increases risk with no tangible benefit to the county tax base.
π The EPA reports a decrease in BESS failure incidents in 2024, citing only eight incidents reported that year across all locations.
ποΈ Alliant stated they will construct the full 25 MW BESS even if the 40 MW amendment is not approved while continuing to work toward an increase.
π€· Supervisor Friday noted the county lacks necessary information from the state regarding a moratorium lift that has been in works for years.
π Union County scheduled a separate public hearing on May 20 for Ordinance 76 concerning partial property tax exemptions for industrial properties.
π The proposed tax exemption schedule is set for five years, starting at 75% in the first year and decreasing by 15% each subsequent year.
- Construction of the Creston Solar and Battery Energy Storage System project is scheduled to begin this month, marking continued progress since the application in 2022.
- Alliant Energy received their construction permit in 2023 for a system generating 40 megawatts, with an additional 25 MW battery energy storage system planned to ensure steady energy flow during fluctuations.
- The foundation for the Battery Energy Storage System (BESS) already broke ground in 2024, with equipment delivery and mobilization set to commence this month.
- Sean Keenan from Alliant stated that if construction proceeds on time, the BESS is operational by December within a six-month timeline.
- The major amendment seeks to expand the MW operating capacity from 25 MWs to 40 MWs while maintaining the same facility space and footprint.
- Alliant Energy has submitted a parental guarantee plan to cover decommissioning costs of approximately $1.757 million, including salvage and disposal fees, addressing safety concerns.
- Emergency plans have been reviewed and approved by Union County EMA Coordinator Paul Ver Meer, with discussions held with the Creston Fire Department regarding lithium battery fire management.
- The Environmental Protection Agency reports a decrease in failure incidents at BESS locations, with only eight incidents reported in 2024 owing to increased grid development.
- Union County is holding a public hearing on May 20 for Ordinance 76 β Industrial Abatement, which would authorize partial property tax exemptions for certain classes of industrial property to encourage development.
- Union County has tabled Alliant Energy's battery expansion project indefinitely, with no review scheduled until Wednesday, May 20, causing a significant delay to the original six-month construction timeline.
- County Supervisor Rick Friday explicitly tied the moratorium on solar energy systems to taxation concerns, stating that expanding the storage without an increase in generation capacity offers 'no benefit' and asks Alliant to consider a different location.
- The county remains hesitant to approve the amendment due to a lack of definitive tax numbers, with estimates deemed insufficient for board approval despite the project having been in motion since 2022.
- Safety concerns persist regarding public risk from lithium battery fires, which are difficult to extinguish and release harmful emissions, leading the fire department to require additional coordination during an incident.
- Supervisor Dennis Hopkins expressed concern over assuming 'more risk' without a corresponding increase in generation tax benefits for the county, questioning the value of expanding storage at the current footprint.
- Alliant faces uncertainty as they may only construct the original 25 MW BESS if the expansion amendment is rejected, leaving significant capital investment on the table while continuing to navigate restrictive moratoriums awaiting state-level clarifications.